Project Status

What's happening at 57 East.

A clear, current look at the work underway, what comes next, and how 57 East will be built over time.

Last updatedAugust 2026
Current Phase

Site Development

Now Underway

2026

57 East is currently in the site development phase. Crews are preparing the property and infrastructure needed before vertical building construction begins.

What does site development mean?

Site development is the physical work required to prepare the property for buildings and supporting infrastructure before vertical construction begins. Work is underway on the property today.

Site Development

What's happening on site?

  1. Now

    Site Preparation

    Grading and preparation continue across different areas of the property.

  2. In Progress

    Utilities + Infrastructure

    Stormwater, water, sewer and underground utility work progresses through the site.

  3. Later in 2026

    Streets + Site Finishes

    Roadway connections, curbs, paving, landscaping and preparation for vertical construction.

Why does one part of the site look different from another?

Site development moves through the property in stages. One area may be undergoing utility work while another is being graded or prepared for the next activity.

90-Day Look Ahead

What you may see on site.

August

Site utilities, grading and stormwater infrastructure continue across the property.

September

Utility and stormwater work progresses into additional areas of the site.

October

Utility installation, roadway connections and site preparation continue.

Construction schedules may shift due to weather, inspections, field conditions and coordination. This page will be updated as work progresses.

Next Up

January 2027

Buildings A + B

Vertical construction of Buildings A and B begins in January 2027, the first structures to rise on the property.

The Road Ahead

From now through 2030.

  1. Now2026

    Site Development

    Current
  2. NextJan 2027

    Buildings A + B

    Vertical Construction
  3. Phased2027-2030

    Additional Buildings

    Phased Buildout
  4. Planned2030

    The Deck at 57

    Planned Start

When it happens

When each part begins.

The same professional plan, viewed by phase. Timing shown here is confirmed; other dates will be added as they are confirmed.

Professional site plan for 57 East, showing confirmed development phases
  1. 2026

    Site Development

    Now Underway

  2. January 2027

    Buildings A + B

    Vertical construction planned

  3. 2027 to 2030

    Additional Development

    As confirmed

  4. 2030

    The Deck at 57

    Planned start

Timing shown is confirmed. Other dates will be added here as they are confirmed.

Phased Development

Why don't all the buildings start at once?

57 East is being built in phases. Buildings A and B begin vertical construction in January 2027. Other buildings will follow between 2027 and 2030 as tenants, users and construction schedules are confirmed. The Deck at 57 is currently planned to begin construction in 2030.

Schedules will be updated here as they are confirmed

How We Got Here

The story so far.

Latest from the Site

The most recent word from the site.

Making Way for a New 57 East Entrance on Salbide Avenue
Current phase: Site Development + InfrastructureConstruction UpdateAugust 12, 2026

Making Way for a New 57 East Entrance on Salbide Avenue

A piece of the former Caldwell Tanks site is coming down this week to make way for a new entrance on Salbide Avenue, while underground infrastructure begins arriving on site.

Read the latest update