Project Status
What's happening at 57 East.
A clear, current look at the work underway, what comes next, and how 57 East will be built over time.
Site Development
Now Underway
2026
57 East is currently in the site development phase. Crews are preparing the property and infrastructure needed before vertical building construction begins.
What does site development mean?
Site development is the physical work required to prepare the property for buildings and supporting infrastructure before vertical construction begins. Work is underway on the property today.
Site Development
What's happening on site?
- Now
Site Preparation
Grading and preparation continue across different areas of the property.
- In Progress
Utilities + Infrastructure
Stormwater, water, sewer and underground utility work progresses through the site.
- Later in 2026
Streets + Site Finishes
Roadway connections, curbs, paving, landscaping and preparation for vertical construction.
Why does one part of the site look different from another?
Site development moves through the property in stages. One area may be undergoing utility work while another is being graded or prepared for the next activity.
90-Day Look Ahead
What you may see on site.
Site utilities, grading and stormwater infrastructure continue across the property.
Utility and stormwater work progresses into additional areas of the site.
Utility installation, roadway connections and site preparation continue.
Construction schedules may shift due to weather, inspections, field conditions and coordination. This page will be updated as work progresses.
January 2027
Buildings A + B
Vertical construction of Buildings A and B begins in January 2027, the first structures to rise on the property.
The Road Ahead
From now through 2030.
- Now2026Current
Site Development
- NextJan 2027Vertical Construction
Buildings A + B
- Phased2027-2030Phased Buildout
Additional Buildings
- Planned2030Planned Start
The Deck at 57
When it happens
When each part begins.
The same professional plan, viewed by phase. Timing shown here is confirmed; other dates will be added as they are confirmed.

2026
Site Development
Now Underway
January 2027
Buildings A + B
Vertical construction planned
2027 to 2030
Additional Development
As confirmed
2030
The Deck at 57
Planned start
Timing shown is confirmed. Other dates will be added here as they are confirmed.
Phased Development
Why don't all the buildings start at once?
57 East is being built in phases. Buildings A and B begin vertical construction in January 2027. Other buildings will follow between 2027 and 2030 as tenants, users and construction schedules are confirmed. The Deck at 57 is currently planned to begin construction in 2030.
Schedules will be updated here as they are confirmed
How We Got Here
The story so far.
Latest from the Site
The most recent word from the site.

Making Way for a New 57 East Entrance on Salbide Avenue
A piece of the former Caldwell Tanks site is coming down this week to make way for a new entrance on Salbide Avenue, while underground infrastructure begins arriving on site.
Read the latest update